Reconstruction of water supply and sewerage system of Salyan
-
Client: Azersu OJSC
-
Project location: Salyan
-
Scope of work: The construction of sewage lines with a length of more than 80 km (DN200-DN800) is planned in the city of Salyan. More than 46 km long drinking water lines (DN90-DN280) have been built. Also, construction of 8 km long microtunnel lines and construction of pumping stations of different capacities on 9 collector lines are planned. The total number of house connections on sewage lines is 5050 units. Construction works are ongoing.
-
Project duration: 2021-2026